Back to Blog

Index of Fun Facts: BPA Planned Power Outage May 9, 2014

Thank you to the OPALCO operations and engineering staff who brought us through this mandatory Bonneville Power Administration county-wide outage! For most of us, this was a smooth and seamless operation. Thanks, also, to the handful of co-op members who were out of power a little longer. This rare transmission outage event gave us the opportunity to really test our system and we found a few weak links. Thank you for your patience and understanding while we addressed those issues; we all benefit from a stronger, more reliable system as a result!

Preparations:

  • 6 weeks to plan the county-wide outage event
  • 9 regional meetings to work out the logistics
  • 42 hours of labor (General Foreman-3, Line Foreman-3, Engineer) on May 8th to prepare for the May 9th outage

The Outage Event:

  • 16 OPALCO personnel working (Lineman-13, General Foreman-2, Dispatcher)
  • 4  Flaggers contracted for safety
  • 15 BPA personnel (Lopez-2, Fidalgo Substation-10, Custer Substation-2, Vancouver, WA-1 )
  • 96 OPALCO crew hours in the field (13 crew x 6 hours) doing maintenance and repair work

Results on OPALCO’s System:

  • 12 transmission poles cleaned and inspected
  • 7 miles of transmission line examined, maintained and tested
  • 6 transmission poles re-built with new insulators
  • 5 high-voltage switches cleaned and tested
  • 4 new distribution switches installed and tested
  • 1 hazardous tree trimmed
  • 14,000 (approximately) members out of power
  • 5 devices (out of 1,200+ total) failed upon restoraton of power (Lopez-2, San Juan-3)
  • 6,000 (approximate total) members restored by 6:15 am
  • 9,000 (approximate total) members restored by 6:30 am
  • 12,000 (approximate total) members restored by 7:00 am. Note: After 7:00 am,
    only Friday Harbor substation remained down, in part due to high system start-up loads.
  • All but 70 members restored by 8:00 am. This restoration delay was in part due to
    high system loads that needed to be managed to prevent a low voltage condition for the entire Island.
  • 18 hours of continuous work by 2 members of our Lopez Crew (Tim Savage and Kai Burleson), who worked from 11:00 pm May 8th until 5:00 PM May 9th – staying on duty
    to restore power to 44 members on Lopez. All other crews were released at 10:00 am
    May 9th.

You may also like...

project status chart

Quick Fact: Preparing for Mainland Power Outages

As OPALCO noted in our 2021 Decarbonization Quick Fact: Carbon emissions have jumped over 30% during the last 100 years. As many as 1 million species are now at risk of … Read more
solar power

The Orcas Island Exchange Harnesses the Power of the Sun

The Exchange – Orcas Island’s unique non-profit transfer station and reuse facility started – generating electricity from the sun on July 2. The nonprofit flipped the switch on a new … Read more
garage

Lopez Garage utilizes Rural Energy Grants for Building Upgrades!

The Lopez Garage business was started way back in 1929 by Lloyd Weeks. He built the building in 1946 and owned it until 1975. Lloyd worked with his son Carroll … Read more