OPALCO LINEMEN REPAIR CABLE IN CASCADE LAKE

A TEAM of linemen from Eastsound repaired an underwater cable that failed in Cascade Lake on Sunday, May 15th. Power was quickly rerouted from the Olga substation to serve those affected by the outage, which last about two hours.

After surveying the situation on Sunday, the crew arrived Monday morning to tackle the problem. Steve Eyler (General Foreman), Dan Watters (Substation Technician), Roger Sandwith (Journeyman Lineman) and Matt Minnis (Apprentice) engineered a creative strategy to locate and repair the damaged cable. First, they located the end of the cable near the shore and dug a trench in the shallows to access it. Then they used the big digger truck to help pull the cable up near the shore, put cable guides on a floating dock section, and then towed the dock along the cable lay pulling the cable up to examine it until the fault was located. They were able to make repairs to the cable on the float, on the lake and restore power later that day.

OPALCO’s distribution system includes 1,146 miles of power lines (82% underground); 14 miles of that is covered by 15 submarine cables. A capital improvement project is underway to lay underground cable around the lake and eventually retire the submarine cable.

OPALCO is a member-owned cooperative electrical utility serving more than 11,000 members on 20 islands in San Juan County. OPALCO provides electricity that is 95% greenhouse-gas free and is predominately generated by hydroelectric plants. OPALCO was founded in 1937 to bring electricity to rural islanders.

You may also like...

spice girls

The Real Spice Girls of Friday Harbor

Volunteerism at the Friday Harbor Food Bank As anyone who lives here knows, non-profit organizations are the lifeblood of the San Juan Islands. San Juan County is home to hundreds … Read more
survey graphic

Quick Fact: OPALCO’s 2025 Renewable Energy Survey

OPALCO’s Renewable Energy Dilemma The 2025 member survey revealed something important: OPALCO members support reliable, affordable, and cleaner electricity — but many of the projects needed to provide that power … Read more
Decatur

OPALCO Receives Conditional Use Permit for the Decatur Island Solar Expansion Project

On Tuesday, May 12, OPALCO was notified that they were granted the Conditional Use Permit for the Decatur Island Solar Expansion Project. The Decatur Island Solar Expansion project is a … Read more