Back to Blog

Pardon our dust: Upcoming construction along Pear Point Road

San Juan County has a recovery strategy for protection of salmon populations which includes the Jackson Beach Restoration Project. As part of the plan, OPALCO is moving the transmission poles off Jackson Beach on San Juan Island. These critical high voltage transmission lines carry power to all of San Juan Island.

Starting early 2025, crews will start by clearing some vegetation along the new route and then will begin setting poles along Pear Point Road and on the Island Rec Gravel Pit parcel so that the three poles on the beach can be removed. Moving the poles off the beach means several of the surrounding poles also need to be moved in order to make this section of the power grid optimally designed.

Once crews get the new transmission poles set, they will install new power lines and splice them to the existing lines. The crew will need to take an all-island outage to energize the lines. Dates will be dependent on work completed and the optimal weather window. Later in 2025, the poles will be removed from the beach.

OPALCO worked closely with Island Rec and the neighborhoods close to this project to find the best route for this critical infrastructure.  OPALCO strives to have minimal impact with these kinds of projects to preserve our pristine environment while providing electricity to our communities.

High voltage power lines like this section of power lines are difficult and expensive to bury underground. Burying transmission lines limits crew access, delays outage restoration, and makes repairs more difficult. OPALCO remains committed to having power lines underground where feasible and more than 89% of our lower voltage distribution lines that feed your house are buried. Keeping the lines clear of vegetation and tall trees is essential to the safety of our crews and to mitigate wildfire risk.

If you have any questions about this project, email communications@opalco.com.

You may also like...

island way

OPALCO Renewable Energy Community Meetings Recap

A few weeks ago, the OPALCO team held a series of community meetings about local, renewable energy. The meetings were held at all three major islands to engage co-op members … Read more
tidal power

Rosario Strait Tidal Energy Project Update

September 30, 2025 is the last day to make public comments on the Rosario Tidal Energy Project as part of the public process with a pilot Draft License Application (DLA) … Read more

Find OPALCO back at their headquarters starting September 29

During the summer months, OPALCO worked on a critical maintenance project for the Eastsound headquarters. The roof of OPALCO’s 1970s built Eastsound headquarters office had reached the end of its … Read more