August 23 to September 2, 2004
Blakely Bore Site
Due to the instability of the hillside at our south end terminal site on Blakely Island, we needed to "bore" through the hillside 140' to 160' feet deep. Two 10" steel ducts were installed using an air compressor to drive a steel bit followed by the pipes into the earth.
The 10' pipe sections were drilled in about 1 1/2', and then they would pause and blow the tailings out of the pipe and proceed to drill again. At the end of each 10' section they would weld on the next pipe and drill again until they arrived at the base of the hill at the shoreline, which they had calculated to a tee!
Armadillo Underground, Inc. of Salem, OR performed the work. One pipe will accommodate the new submarine cable that was installed in October and the other will be for a future installation.
Click on a photo to view a larger and more detailed version
Below: Steel pipe section being drilled into the hillside
Below-Right: The tailings being blown out
Below-Left: Placing the next pipe in line
Below: Welding two pipe sections together